A 20 ton overhead crane is a bridge crane rated to lift 20,000 kg, and a 16 ton crane lifts 16,000 kg; at this size the main design decision is whether one girder is still enough or two are needed. Typical spans run from 10.5 m to 34.5 m, and FOB China prices run from $25,000 to $62,000 depending on girder type, span and duty class.
The short answer: a single girder crane still works at 16 – 20 t for shorter spans and light to medium duty, while a double girder becomes the default once the span passes about 16.5 m, the duty class reaches A5 or above, or you need every metre of hook height. The rest of this guide shows where that line sits and what it means for your runway and budget.
Get a drawing and quoteJump to the selection checklist

| Item | 16 ton overhead crane | 20 ton overhead crane |
|---|---|---|
| Rated capacity | 16,000 kg | 20,000 kg |
| Girder options | Single girder (LD or European-type) on shorter spans; double girder (QD or European-type) | Single girder up to about 16.5 m span; double girder (QD or European-type) beyond that |
| Span | Single girder up to 16.5 m; double girder 10.5 – 34.5 m | 10.5 – 34.5 m, European-type double girder |
| Lifting height | Typically 6 – 12 m; higher on request | Typically 6 – 12 m; higher on request |
| Duty class | A3 – A5 single girder; A5 – A6 double girder; A7 with a winch trolley | Same |
| Hoist / trolley | European-type wire rope hoist; open winch trolley on QD double girder | European-type wire rope hoist; open winch trolley on QD double girder |
| Lifting speed | About 5 m/min main speed with a creep speed; VFD for stepless control | Same |
| Crane travel speed | Up to 0 – 40 m/min with VFD | Up to 0 – 40 m/min with VFD |
| Power supply | 380 – 415 V, 50 / 60 Hz, 3-phase, to your site standard | Same |
| Runway rail | Sized to suit the wheel load — specified on the GA drawing with your quote | P22 up to 16.5 m span; P30 from 19.5 m (European-type double girder) |
| Max wheel load, 16.5 m span | Calculated for your span and capacity — shown on the GA drawing | 66.9 kN per wheel on 8 wheels (European-type double girder) |
| Crane weight, 16.5 m span | Calculated for your span and capacity — shown on the GA drawing | 9.45 t, including a 1.07 t trolley (European-type double girder) |
The 20 ton figures come from our European-type double girder spec sheet. A crane at this size usually runs on eight wheels, two per corner, so the load per wheel stays moderate. We issue exact figures with the general arrangement drawing for your span and lifting height.
At 5 – 10 t a single girder is the obvious choice for most workshops. At 16 – 20 t it is a real decision, and the right answer depends on span, duty and hook height more than on capacity alone. For a general comparison across all sizes, see choosing between single and double girder cranes.
A single girder crane still makes sense when:
A double girder crane is the better choice when:
Double girder does not have to mean heavy. Our European-type double girder crane at 20 t and 16.5 m span weighs 9.45 t in total, with a 1.07 t hoist trolley.
| European-type double girder | QD double girder | |
|---|---|---|
| Trolley | Compact wire rope hoist trolley | Open winch trolley — drum, gearbox and brake on the trolley frame |
| Weight and wheel loads | Lighter girder and trolley, lower wheel loads | Heavier; higher wheel loads |
| Headroom | Low-headroom trolley, more hook height in a low building | Taller trolley, needs more roof clearance |
| Duty | A5 – A8 typical | A5 – A7; suits continuous heavy duty |
| Price | Higher | Lower |
European-type cranes are the better fit for new buildings, where lighter wheel loads save runway steel. QD cranes with an open winch trolley suit steel plants and continuous heavy duty, where the mechanism is easy to reach and maintain. See our QD double girder overhead crane and, for lighter duty, the European-type single girder range up to 20 t and the LD single girder crane.
Duty class matters as much as capacity at this size. If you are unsure whether your process is A5 or A6, our guide to crane hoist duty classification explains how lifts per hour and average load decide it.

A 16 – 20 t crane puts real load into the building. Before you request a quote, confirm these points:

If the girders and runway are sound, a new crane is not always the answer. For a steel plant in Kenya we first supplied a single 16 t hoist trolley package as a trial unit, installed by the plant's own team with remote guidance; two years later the customer ordered the upgrade of four double girder cranes to A7 duty.
Need a first girder size for your structural engineer? Try our Girder Pre-Sizing Estimator.
| Configuration | FOB China price |
|---|---|
| 16 t single girder LD, span up to 16.5 m | $15,000 – $21,000 |
| 20 t single girder LD or European-type, span up to 16.5 m | $23,000 – $29,000 |
| 16 t double girder QD, span 16.5 – 22.5 m | $26,000 – $35,000 |
| 20 t double girder QD, span 16.5 – 22.5 m | $30,000 – $41,000 |
| 20 t European-type double girder, 16.5 m span | $34,000 – $39,000 |
| 20 t European-type double girder, 22.5 – 28.5 m span | $40,000 – $58,000 |
Prices exclude runway rails, installation and freight. The step from 16 t to 20 t in the same configuration usually adds 15% - 25% (approx. 4,000–7,000 USD). More capacities are covered on our overhead crane price page.
What moves the price:

For lighter loads, see our 5 ton & 10 ton overhead crane guide.
A 20 ton overhead crane costs $ 34,000 to $ 62,000 FOB China, depending mainly on girder type, span and duty class. Add runway rail, freight and installation for the landed cost.
Yes, on shorter spans — up to about 16.5 m — and light to medium duty. Beyond that span, at A5 duty and above, or where hook height matters, a double girder is the safer choice.
Our 20 t European-type double girder crane has a maximum wheel load of 66.9 kN per wheel at 16.5 m span, on eight wheels, rising to 81.3 kN at 28.5 m. Exact values depend on span, trolley and duty and are shown on the drawing.
For our European-type double girder crane, P22 up to 16.5 m span and P30 from 19.5 m. QD cranes with a winch trolley usually need a heavier rail, confirmed on the drawing.
Size for your heaviest load including attachments, then look ahead. If loads are close to 16 t or likely to grow, a 20 t crane costs around 15% – 20% more and saves rebuilding the runway later.
Send us your span, lifting height and duty cycle — we return a drawing and quote within 24 hours. The general arrangement drawing includes the wheel loads your runway designer needs.
Kino Cranes has built overhead cranes for 18+ years, with 5,000+ projects delivered to 120+ countries from a 150,000 m² factory.
Describe your load and building in one email — our engineers recommend the right crane type and configuration within 24 hours.
TO TOP